COMMISSIONING AND TESTING OF WWTP AT RWANDA NATIONAL ARCHIVE at KACYIRU

Commissioning Team
The Contractor were represented by Fair construction’s Project Manager and Pyramid Consultancy members.
Star Construction were represented by Managing director and Quality Assurance Manager.
The event took place on 12/07/2021 at Rwanda national Archive at Kacyiru
Commissioning and Testing Objective
The objectives or aims of that event was to ensure and document all system perform interactively according to the design and the owner’s operational needs. The commissioning process includes documentation, equipment start-up, control system calibration, testing, performance testing and training.
The commissioned STP Technical Data
Brand name: BIOKUBE Bioreactor 75 one unit
The System is installed to Treat effluent from Office Building. The System was designed to Treat mixed effluent (Black and Grey) water from the buildings. The Specialty of the System is that it is equipped with a SCADA System that facilitate the remote control of the Unit. Effluent from the System passes through a series of Sand Filters and Chlorination. Treated water is ready for safe discharge.
Capacity: 40 m3 per day
Contractor’s team were satisfied by the results of the STP performance.

The above pictures were taken during the test and commissioning