COMMISSIONING AND TESTING OF WWTP AT WELLSPRING ACADEMY at NYARUTARAMA

Commissioning Team

The Contractor were represented by Principal of school and Director of Administration Finance

Star Construction were represented by Chairman of Board, Managing director, Production Manager and Quality Assurance Manager.

The event took place on Monday 14/06/2021 at Wellsprings Academy at Nyarutarama

Commissioning and Testing Objective  

The objectives or aims of that event was to ensure and document all system perform interactively according to the design and the owner’s operational needs. The commissioning process includes documentation, equipment startup, control system calibration, testing, performance testing and training.

The commissioned STP Technical Data:

The System is installed to Treat effluent from Schools Building. The System was designed to Treat mixed effluent (Black and Grey) water from the mentioned   buildings.

Brand name: BIOKUBE Pluto system

Capacity: 2m3 per day

The commissioned STP is the first phase among three phases planed for that project.

Contractor’s team were satisfied by the results of STP performance.