RWANDA NATIONAL ARCHIVES WWTP

RWANDA NATIONAL ARCHIVES WWTP

IN LIQUID WASTE MANAGEMENT
Client Name:
FAIR CONSTRUCTION
Construction Date:
March 31, 2021
Location:
Gasabo District-Rwanda
Value:
Nature of Contract:
Sub Contractor
About Project

Product Type: Biokube Bioreactor 75

Application: Office Building

Capacity [M³/day]: 160

Status: Installation activities are Ongoing.

Description: The System is installed to Treat effluent from Office Building. The System was designed to Treat mixed effluent (Black and Grey) water from the Buildings. The Specialty of the System is that it is equipped with a SCADA System that facilitate the remote control of the Unit. Effluent from the System passes through a series of Sand Filters and UV System. Treated water is ready for reuse in Gardening in the compound or safe discharge. The above picture was taken during the system installation .